Platform Leg Decommissioning Completed in 7 Months


Client Leading offshore asset owner
Region Middle East
Year 2019
Service details

Our decommissioning services reflect the priorities and objectives of the modern-day industry. Our products are designed and manufactured to cut a wide range of materials and structures and are ideally suited for underwater deployment by either ROV or diver operations.

To know more, get in touch with us enquiries@wellube.com

Summary of the Project

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
We faced challenges pertaining to the timeline and operational accessibility of the project as,
  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.

Challenges Faced For Platform Leg Decommissioning

We faced challenges pertaining to the timeline and operational accessibility of the project as,

  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
Monopod freestanding prior to decommissioning

Challenges Faced For Platform Leg Decommissioning

We faced challenges pertaining to the timeline and operational accessibility of the project as,

  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
Our client approached Wellube to perform Platform Leg decommissioning and maintenance of several assets on their offshore platforms. We were asked to perform decommissioning of 36 monopod, tripod, production platform, and flare tower Legs as well as hot tapping on annulus in wellhead at the platform.

Monopod freestanding prior to decommissioning

Challenges Faced For Platform Leg Decommissioning

We faced challenges pertaining to the timeline and operational accessibility of the project as,

  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.

Client Requirement – Platform Leg Decommissioning

Our client approached Wellube to perform Platform Leg decommissioning and maintenance of several assets on their offshore platforms. We were asked to perform decommissioning of 36 monopod, tripod, production platform, and flare tower Legs as well as hot tapping on annulus in wellhead at the platform.

Monopod freestanding prior to decommissioning

Challenges Faced For Platform Leg Decommissioning

We faced challenges pertaining to the timeline and operational accessibility of the project as,

  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
The Central Production Platform (CPP)

Client Requirement – Platform Leg Decommissioning

Our client approached Wellube to perform Platform Leg decommissioning and maintenance of several assets on their offshore platforms. We were asked to perform decommissioning of 36 monopod, tripod, production platform, and flare tower Legs as well as hot tapping on annulus in wellhead at the platform.

Monopod freestanding prior to decommissioning

Challenges Faced For Platform Leg Decommissioning

We faced challenges pertaining to the timeline and operational accessibility of the project as,

  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
Wellube has performed Platform Leg Decommissioning of several assets on the offshore platforms of a leading asset owner using a diamond wire cutting method in the Middle East.

The Central Production Platform (CPP)

Client Requirement – Platform Leg Decommissioning

Our client approached Wellube to perform Platform Leg decommissioning and maintenance of several assets on their offshore platforms. We were asked to perform decommissioning of 36 monopod, tripod, production platform, and flare tower Legs as well as hot tapping on annulus in wellhead at the platform.

Monopod freestanding prior to decommissioning

Challenges Faced For Platform Leg Decommissioning

We faced challenges pertaining to the timeline and operational accessibility of the project as,

  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.

Wellube has performed Platform Leg Decommissioning of several assets on the offshore platforms of a leading asset owner using a diamond wire cutting method in the Middle East.

The Central Production Platform (CPP)

Client Requirement – Platform Leg Decommissioning

Our client approached Wellube to perform Platform Leg decommissioning and maintenance of several assets on their offshore platforms. We were asked to perform decommissioning of 36 monopod, tripod, production platform, and flare tower Legs as well as hot tapping on annulus in wellhead at the platform.

Monopod freestanding prior to decommissioning

Challenges Faced For Platform Leg Decommissioning

We faced challenges pertaining to the timeline and operational accessibility of the project as,

  • The project needed to be executed within a minimum period of 7 months
  • Some platforms and towers needed to be decommissioned using the diamond wire cutting saw and there was very less clearance gap available for all the platform legs to mount the equipment.

View of the Central Production Platform (CPP)

Unique Solution Delivered

After evaluation of the project details, we decided to utilise a 50” diamond wire cutting saw connected on deck via umbilical bundle to perform the Platform Leg decommissioning. As the cuts needed for the platform legs were deep sea, the equipment had to be modified to suit the clearance gap.

We decided on using the diamond wire cutting method because it is compact, portable and convenient to maneuver and position as required.

Following the successful completion of our initial contract, the client included additional scope extending the project for a longer period. The client was satisfied with our execution of the project smoothly.

Flare Tower supporting jacket

Benefits Delivered

  • Completed within the specified timeframe.
  • Executed in a safe and eco-friendly method.
  • Customised equipment to suit client site conditions.
Jiju Vijayakumar

Share
Published by
Jiju Vijayakumar

Recent Posts

25 Bar, 350 °C Steam Leak Successfully Sealed in UAE

Before After Client Dubai Electricity & Water Authority (DEWA) - Power & Utilities Industry Country…

3 weeks ago

Online Leak Sealing on Wellhead Flange Leak in Costa Rica

Before In-Progress After Client Geochem (Geo Thermal – Energy Industry) Country Costa Rica Year 2022…

2 months ago

Front-End Engineering Design and 14” Hot Tapping on 42” & 52” Natural Gas Pipeline

Client Oil & Gas Client Country United Arab Emirates (UAE) Year 2024 Details Hot tapping…

2 months ago

Redefining Pipeline Intervention

As featured in World Pipelines Magazine - discover how Wellube is redefining pipeline intervention with…

5 months ago

42” Hot Tapping on 48” #600 Crude Oil Pipeline and 64” #150 Ship Loading Pipeline

Client SK Engineering and Construction (SKEC) Country Fujairah, United Arab Emirates (UAE) Year 2023 Details…

7 months ago

24” Leaking Offshore Gas Pipeline Arrested Using Online Leak Sealing Solution

Client Leading Offshore Oil and Gas Company Country United Arab Emirates (UAE) Year 2021-2022 Details…

7 months ago