Client | Leading Petrochemical Company |
Country | Sudan |
Year | 2020 |
Service Details | Wellube’s Hot tapping and Line stopping service is a cost-effective way of enabling repairs, maintenance, modifications, or reconfiguration work on existing piping systems – on either a planned or emergency basis. Our solution prevents unwanted shutdowns and keeps critical piping and pipeline systems online during tie-ins, relocations, repairs, retrofits, and routine maintenance. Get in touch with us at enquiries@wellube.com |
Wellube completed a double position line stop operation on a 32” gas flare line to install a butterfly valve and tie-in valve in the existing flare line for a petrochemical client in Sudan. This project also holds the remarkable achievement of being the first of its kind in North Sudan.
The client needed to perform maintenance in the header pipe of the client’s refinery flare header, which was the only flaring line for the two refineries in the facility. To enable this, a new branch had to be introduced and a butterfly valve as well as tie-in valve had to be installed on the new flaring line. The client reached out to Wellube to support them as hot tapping and line stopping was needed to execute their requirement.
As part of our complete turnkey solution, we provided fit-up of the split tees, in-service welding, hot tap & line stop including secondary bag isolation at two locations and pipe cutting of the 32” to install the Butterfly valve.
Wellube performed line stopping on the existing flare line with a bypass of 16” and welding of WNRF flanges for installation of the new butterfly valve without interruption to the flow in the line.
The size of the pipeline being an odd size 32”, we provided the client the optimum solution by engineering the requirements based on the site conditions and our equipment, which enabled us to complete the project within the client schedule.
The client was completely satisfied with our service and appreciated Wellube’s technical excellence and professionalism.
As the project has been successfully completed, the client can now perform maintenance of their completely dependent only available flare header connected to the two refineries without complete shutdown of the refinery and production loss.
Before After Client Dubai Electricity & Water Authority (DEWA) - Power & Utilities Industry Country…
Before In-Progress After Client Geochem (Geo Thermal – Energy Industry) Country Costa Rica Year 2022…
Client Oil & Gas Client Country United Arab Emirates (UAE) Year 2024 Details Hot tapping…
As featured in World Pipelines Magazine - discover how Wellube is redefining pipeline intervention with…
Client SK Engineering and Construction (SKEC) Country Fujairah, United Arab Emirates (UAE) Year 2023 Details…
Client Leading Offshore Oil and Gas Company Country United Arab Emirates (UAE) Year 2021-2022 Details…