Wellube successfully delivered a comprehensive turnkey online leak sealing solution for a leading oil and gas client, ensuring uninterrupted operations and enhanced reliability. The project involved 41 leak repair clamps across 15 locations on a 24” (DN600) pipeline. We provided a full solution, from technical consultation and engineering design to fabrication and on-site implementation, addressing leaks without the need for a costly shutdown. The client faced multiple leaks and wall thinning in their pipeline and required a prompt, shutdown-free solution to maintain production. Wellube’s swift response, enabled by our in-house manufacturing capabilities and stock of semi-finished clamps, ensured minimal disruption to operations. Our specially formulated compounds, compatible with various line mediums and temperatures, reinforced pipeline integrity and mitigated environmental impact. This end-to-end approach not only resolved immediate issues but also strengthened the system, preventing unplanned shutdowns in the flare system and enhancing asset longevity.

To know more, contact us

Project Summary

Wellube successfully provided a turnkey online leak sealing solution ensuring uninterrupted operations and enhanced reliability for a leading client in the oil and gas industry. The project required 41 leak repair clamps at 15 different locations of 24” (DN600) diameter. We provided an end-to-end solution including design, fabrication and installation of equipment to promptly address the leaks and prevent unplanned shutdowns in the flare system.

Client Requirement

The client encountered leaks and wall thinning issues at multiple locations in their pipeline. Due to the time-consuming nature of replacing the pipeline and the associated costs involved with production loss, shutdown was not feasible. The client required a solution without shutdown to promptly address leaks, while also strengthening the integrity of the pipeline.

Challenges faced

The primary challenge revolved around time constraints, intensified by the criticality of the piping system being the flare line. The leak not only posed environmental concerns but also resulted in significant downtime and loss of production, increasing the urgency for a swift and effective solution.

Bespoke Solution Delivered

Leveraging our advanced global engineering design – “Centre of Excellence” team and proficient project management capabilities, Wellube swiftly provided an online leak solution along with the quickest possible and mutually acceptable time frame to execute the required site work.

Following the acceptance of the proposal, Wellube conducted a detailed site survey to gather requirements at 15 different locations for the design of 41 online leak sealing clamps. Once the design was approved, we commenced with the fabrication process, which included various stages such as fabrication itself, Non-Destructive Examination (NDE), Post Weld Heat Treatment (PWHT), hardness testing, and Magnetic Particle Examination (MPE). Subsequently, a Factory Acceptance Test (FAT) was conducted for the clamp to ensure its functionality. Finally, the clamp underwent painting and packaging processes.

Upon arrival of the clamp at the site, the Wellube team was deployed to execute the installation process and perform sealant injection as required. In instances where leaks couldn’t be visually identified due to wall thinning, Wellube conducted leak tests to ensure that in the event of a pipe leak, the clamp would effectively withstand pressure and prevent gas from escaping. Following the completion of the job, a thorough walk-through was conducted with the client to verify that the project had been executed in accordance with the specified requirements.

Benefits Delivered

  • The project was completed without interrupting or halting the LIVE pipeline.
  • The project was executed with complete QHSE compliance and safety.
  • End to end project management by Wellube team providing clients a one point of contact integrated solution
  • Completed the project on-time-in-full and as per codes.
Shyam Karthik Kothandaraman

Share
Published by
Shyam Karthik Kothandaraman

Recent Posts

25 Bar, 350 °C Steam Leak Successfully Sealed in UAE

Before After Client Dubai Electricity & Water Authority (DEWA) - Power & Utilities Industry Country…

3 weeks ago

Online Leak Sealing on Wellhead Flange Leak in Costa Rica

Before In-Progress After Client Geochem (Geo Thermal – Energy Industry) Country Costa Rica Year 2022…

2 months ago

Front-End Engineering Design and 14” Hot Tapping on 42” & 52” Natural Gas Pipeline

Client Oil & Gas Client Country United Arab Emirates (UAE) Year 2024 Details Hot tapping…

2 months ago

Redefining Pipeline Intervention

As featured in World Pipelines Magazine - discover how Wellube is redefining pipeline intervention with…

5 months ago

42” Hot Tapping on 48” #600 Crude Oil Pipeline and 64” #150 Ship Loading Pipeline

Client SK Engineering and Construction (SKEC) Country Fujairah, United Arab Emirates (UAE) Year 2023 Details…

7 months ago

Essential Guide to Valve Maintenance: Best Practices & Expert Tips

Valves are important fluid control systems across a wide range of industries, from oil and…

7 months ago