Service details A leak from a piping system during operation can lead to the escape of line medium into the atmosphere and, depending on the severity of the leak, it could lead to an unplanned & costly shutdown. Wellube maintains a stock of semi-finished clamps and our in-house manufacturing facilities enables us to provide a quick turnaround to arrest leaks with minimal loss of production and environmental impact. Our selection of specially formulated compounds is compatible with most line mediums & temperatures encountered in normal plant operations. To know more, get in touch with us at enquiries@wellube.com

Project Summary

Wellube has successfully sealed a leak in a wellhead master valve flange on a live pipeline which was operating between 1000 – 2000 psi and at a temperature of 200° C. The entire operation was carried out without shutting down the well, thus ensuring seamless operation for KenGen.

Leak arrested on the wellhead master valve flange with a ring clamp

Client Requirement

The client had a steam leak at one of the geothermal wells in Olkaria, Kenya. The leak was from the Master Valve Flange Joint which was operating between 1000 and 2000 psi at an operating temperature of 200 deg C. Wellube was asked to provide a solution that can be implemented without shutdown of the operating well and which will avoid quenching of the valve.

The leaking master valve flange

Challenges Faced

  • There was no means to regulate the upstream steam flow, which was generated from the deep reservoir underground, this resulted in pressure and temperature fluctuations in the line.
  • Silica particles were being entrapped in the flange bolt holes which presented difficulty in getting the sealant compound injected into the flange cavity to travel through the bolt holes. To solve this challenge, additional injection points were used on the flange periphery to ensure the injected sealant would travel through the flange bolt hole cavity to prevent the re-occurrence of leakage through the flange bolt holes in the future.

Solution Engineered

Wellube after analysis of the requirement, performed a detailed site survey to obtain the required field dimensions of the leaking flange joint and the nearest obstruction to determine the best possible solution. After the survey, it was determined that a ring clamp would be installed that would fit in the gap between the flanges followed by injection of suitable sealant compounds. The flange insert-lip clamp was designed according to ASME Sec VIII DIV 1, this was clamped around the flange.

Ring clamp installation in progress to seal the leak

Design and manufacturing of the clamp were completed within 48 hours, following which the team was mobilized to the site along with the clamp, equipment and accessories. The leak was successfully arrested to the satisfaction of KenGen personnel at the site. By completing the work online, KenGen managed to avoid taking a well offline and prevented the inherent risk of quenching the well which may have resulted in the complete loss of well.

Benefits Delivered

  • Completed the project within schedule
  • Avoided shutdown of the well, thus ensuring production continuity
  • Quick and efficient solution
  • Achieved 100% seal on the line.
  • Fully HSEQ compliant
Jiju Vijayakumar

Share
Published by
Jiju Vijayakumar

Recent Posts

25 Bar, 350 °C Steam Leak Successfully Sealed in UAE

Before After Client Dubai Electricity & Water Authority (DEWA) - Power & Utilities Industry Country…

3 weeks ago

Online Leak Sealing on Wellhead Flange Leak in Costa Rica

Before In-Progress After Client Geochem (Geo Thermal – Energy Industry) Country Costa Rica Year 2022…

2 months ago

Front-End Engineering Design and 14” Hot Tapping on 42” & 52” Natural Gas Pipeline

Client Oil & Gas Client Country United Arab Emirates (UAE) Year 2024 Details Hot tapping…

2 months ago

Redefining Pipeline Intervention

As featured in World Pipelines Magazine - discover how Wellube is redefining pipeline intervention with…

5 months ago

42” Hot Tapping on 48” #600 Crude Oil Pipeline and 64” #150 Ship Loading Pipeline

Client SK Engineering and Construction (SKEC) Country Fujairah, United Arab Emirates (UAE) Year 2023 Details…

7 months ago

24” Leaking Offshore Gas Pipeline Arrested Using Online Leak Sealing Solution

Client Leading Offshore Oil and Gas Company Country United Arab Emirates (UAE) Year 2021-2022 Details…

7 months ago