Performed hot tap operation on a 48” ductile iron water pipeline to install new connections.
The whole operation is completed while the line is “live” or in its normal operating conditions.
Completed a double position line stop operation on a 32” gas flare.
Hot tapping and line stopping was performed with a customised mechanical head.
Successfully completed energy efficiency measures on a major infrastructure in the UAE.
Wellube helped the client restore production with minimal downtime.
Wellube successfully completed online sealing of 68” expansion bellow sea water leak in Abu Dhabi.
Wellube has announced the appointment of Garry Kidd and completion of rebrand.
This project is a line stop operation involving isolation of 30” cooling water lines at 3 locations.
The scope involved supply of the equipment, training of personnel in operation & maintenance.